Verified Atlas / Data Centers
Built from the live database: September 14, 202657 instruments · 79 facilities · 212 claims · 1036 sourcesall with quote and pinpointEvery value on this page comes from a row in that snapshot.
View
Citable provisions first: exit and collateral language with quote and pinpoint, then the open dockets you have to re-check.

Atlas / Missouri / record

City of Liberty Planning & Zoning / City Council Approval and Real & Personal Property Tax Abatement Ordinance for the Metrobloks Industrial Development Project

single-reviewer ordinance enacted mo-liberty-city-metrobloks-industrial-dev-2025

Record created 2026-08-21, last updated 2026-08-21. Snapshot built September 14, 2026. JSON

Fields, as recorded

State
MO
Kind
ordinance
Status
enacted
Agency
City of Liberty, Missouri (Planning & Zoning Commission; City Council)
Citation
City of Liberty Planning & Zoning Commission review December 9, 2025; City Council approval (by ordinance) December 15, 2025; a related 'Ordinance' (property tax abatement / industrial development plan) and 'Plan for Industrial Development Project for the Metrobloks Project' were posted to the City Council's CivicClerk meeting portal on March 19, 2026 ahead of a March 23, 2026 Council meeting, per libertymissouri.gov's own Metrobloks FAQ page. The underlying ordinance PDF itself lives behind a CivicClerk JavaScript SPA portal (libertymo.portal.civicclerk.com) that was NOT raw-fetchable this tick (attachment endpoints return the SPA's index.html shell, not the document; no public document API endpoint was found in the time available) -- exact ordinance/bill number not recovered. This is distinct from the Missouri Empire District Electric Co. d/b/a Liberty UTILITY's large-load tariff docket (mo-liberty-llt-et-2026-0184) already on file in this corpus -- 'Liberty' here is the City of Liberty, Clay County, MO, not the electric utility.
Effective
2025-12-15
Contract term (years)
25
Mandatory
False
Summary
Per the City of Liberty's own official Metrobloks FAQ page (libertymissouri.gov/2793/Metrobloks-FAQs, already partially on file in this corpus for the facility row metrobloks-liberty-clay, re-fetched this tick for instrument-level detail): the project was processed as an industrial zoning matter, not a rezoning -- 'As this project was proposed for an industrial zoning district, it was processed as an industrial development... The Planning & Zoning Commission met regarding this project on December 9, 2025. The City Council took up and approved this project on December 15, 2025, both of these meetings included a public hearing for the public to comment.' State-law notice was given: 'Legal Notice printed in Courier Tribune - November 19', letters to property owners within 185 ft. on November 20, and on-site signage November 20. Separately, the FAQ documents a real-and-personal-property tax abatement financed via industrial revenue bonds: 'The project will have abatements on real and personal property taxes. The total cost of the project is estimated to be $1.4 billion, consisting of approximately $543 million in real property improvements and $858 million in personal property... Over the life of the 25-year abatement, taxing jurisdictions will receive approximately $49 million, with Liberty Public Schools receiving approximately $30 million of that. Without this project, this property would only generate a total of $34,000 in taxes for all taxing jurisdictions in the county over the next 25 years.' (two slightly different 'without this project' baseline figures appear on the same FAQ page -- '$35,000... and only $26,000' in one answer, '$34,000' in another -- both recorded verbatim as an internal inconsistency in the city's own page, not resolved by us.) The FAQ also confirms 'the City does not "back" private sector bonds. The developer is solely responsible for the repayment of the bonds' -- i.e., industrial revenue bonds (a standard MO Chapter 100-style vehicle), not general-obligation debt. A related, separately-approved Community Benefits Agreement (a $27.75 million, 25-year contribution to the newly formed Liberty Institute for Science and Ethics, already on file via the City's March 24, 2026 news release in collect-mo-maintenance-2026-08-20.json) is corroborating context, not the subject of this row. DED's own March 24, 2026 press release on the same project corroborates the layered-incentive structure without detailing it: Michelle Hataway (DED Director) credited 'the support of regional, local, and state incentives' -- this City ordinance being the 'local' layer, mo-data-center-sales-tax-exemption-144810 the 'state' layer named explicitly in the same release. The relationship (whether both apply concurrently, and to what value) is not asserted here.
Cost allocation
Over the life of the 25-year abatement, taxing jurisdictions will receive approximately $49 million, with Liberty Public Schools receiving approximately $30 million of that. Without this project, this property would provide less than $35,000 to all taxing jurisdictions and only $26,000 to the Liberty Public School District.

Sources

3 rows, every one with a quote and a pinpoint. 3 quotes open here
  • Metrobloks FAQs | the City of Liberty Official Website! government single-reviewer

    “As with every application that comes to the City there is an internal review process that considers a variety of factors including zoning, utility impacts and City Codes. Under current Liberty code, data centers are classified similarly to other industrial buildings. As this project was proposed for an industrial zoning district, it was processed as an industrial development. ... The Planning & Zoning Commission met regarding this project on December 9, 2025. The City Council took up and approved this project on December 15, 2025, both of these meetings included a public hearing for the public to comment.”

    ‘What was the process for approving this project?’ answer
    https://www.libertymissouri.gov/2793/Metrobloks-FAQs
    Raw curl fetch. Ellipsis marks one omitted intervening sentence (about the Amazon/Walgreens comparison buildings), each half individually contiguous verbatim text. Grounds the zoning-process description and the Dec. 9/Dec. 15, 2025 dates (also already on file for the facility row, re-cited here at the instrument level).

  • Metrobloks FAQs | the City of Liberty Official Website! government single-reviewer

    “The project will have abatements on real and personal property taxes. The total cost of the project is estimated to be $1.4 billion, consisting of approximately $543 million in real property improvements and $858 million in personal property.”

    ‘Are tax incentives provided for this development?’ answer
    https://www.libertymissouri.gov/2793/Metrobloks-FAQs
    Grounds the real/personal property tax abatement mechanism and project cost breakdown. Note the FAQ page states a different 'without this project' 25-year tax baseline in this answer ($34,000) than in the 'What are the benefits' answer used for the cost_allocation field and claim_ref 6 ($35,000/$26,000 split by jurisdiction) -- both figures are the City's own, and both are preserved verbatim rather than reconciled.

  • Metrobloks FAQs | the City of Liberty Official Website! government single-reviewer

    “No. The City does not “back” private sector bonds. The developer is solely responsible for the repayment of the bonds. Taxpayers have no responsibility for the repayment of the bonds.”

    ‘Is the City “backing” the industrial revenue bonds’ answer, and 'Related documents' links under the tax-incentive and Community Benefits Agreement questions
    https://www.libertymissouri.gov/2793/Metrobloks-FAQs
    Confirms the abatement is financed via industrial revenue bonds, a standard Missouri municipal incentive vehicle (consistent with a Chapter 100-style plan, though the FAQ page does not itself cite RSMo Chapter 100 by number). The same FAQ page links three source PDFs -- 'City Council Action Report', 'Ordinance', and 'Plan for Industrial Development Project for the Metrobloks Project' -- hosted on a CivicClerk JavaScript portal (libertymo.portal.civicclerk.com/event/568/files/...) that returns only the SPA's index.html shell on a raw curl fetch, not the underlying PDF; the ordinance's own text and bill number were not recovered this tick (open item for a future MO tick, similar to other JS-portal document blocks already in this corpus's toolkit notes).

Claims attached to this record

  • City of Liberty (official Metrobloks FAQ page) tax_revenue

    “Over the life of the 25-year abatement, taxing jurisdictions will receive approximately $49 million, with Liberty Public Schools receiving approximately $30 million of that. Without this project, this property would provide less than $35,000 to all taxing jurisdictions and only $26,000 to the Liberty Public School District.”