Liberty Utilities Large Load Tariff Case
two-reviewer docket pending mo-liberty-llt-et-2026-0184
Record created 2026-08-16, last updated 2026-08-16. Snapshot built September 14, 2026. JSON
Fields, as recorded
- State
- MO
- Kind
- docket
- Status
- pending
- Agency
- Missouri Public Service Commission
- Utility
- Liberty Utilities
- Citation
- Case No. ET-2026-0184 (Mo. P.S.C., pending)
- Docket
- ET-2026-0184
- Summary
- The PSC's large-load-tariff page identifies a pending case for Liberty Utilities' large-load tariff, docket ET-2026-0184, and directs public comments to the PSC's public comment portal. No approved terms were located as of collection. MO GATE 2026-08-20: Docket sheet fetched directly this gate (efis.psc.mo.gov/Display/ET-2026-0184): Status Open (1/16/2026), styled 'In the Matter of The Empire District Electric Company d/b/a Liberty's Application for Approval of New or Modified Tariffs for Service to Large Load Customers.' Two extensions of time granted at Liberty's request (7/2/2026 and 8/13/2026) with a Motion for Expedited Treatment filed 8/13/2026; no tariff terms approved, so every term field correctly remains null. This is the most active MO large-load docket.
Sources
4 rows, every one with a quote and a pinpoint. 4 quotes open here- Docket Sheet - ET-2026-0184 - EFIS docket two-reviewer
“Status Open (1/16/2026) ... Style of Case In the Matter of The Empire District Electric Company d/b/a Liberty's Application for Approval of New or Modified Tariffs for Service to Large Load Customers ... Item No. Date Filed Type of Filing Title of Filing Filed on Behalf of Response to Previous Filings 8 2026-08-13 14:25 8/13/2026 2:25 PM Order Second Order Granting Request for an Extension Commission (Other) 6 , 7 7 2026-08-13 10:26 8/13/2026 10:26 AM Motion Motion for Expedited Treatment Empire District Electric Company, The (Electric) (Investor) Liberty (Empire) (Electric) (Investor) 6 6 2026-08-11 13:53 8/11/2026 1:53 PM Motion Second Motion for Extension of Time Empire District Electric Company, The (Electric) (Investor) Liberty (Empire) (Electric) (Investor) 5 2026-07-02 09:02 7/2/2026 9:02 AM Order Order Granting Request for an Extension Commission (Other) 4 4 2026-07-01 12:41 7/1/2026 12:41 PM Motion Motion for Extension of Time”
Status field; Style of Case; Docket Filings table, Item Nos. 1-8
https://efis.psc.mo.gov/Display/ET-2026-0184
MAINTENANCE RE-READ 2026-08-20 -- TOOLKIT DISCOVERY: efis.psc.mo.gov also resolves case docket sheets directly by case number at /Display/{CASE-NO} (e.g. /Display/ET-2026-0184), not only by internal numeric Case/Display/{id}; useful when the internal id is unknown. This is the first time this docket's own filing history has been fetched (the original collection only cited the PSC's static large-load-tariff overview page for Liberty). NEW ORDERS/MOVEMENT found: two extensions of time have been granted at Liberty's own request (Order Granting Request for an Extension, 7/2/2026; Second Order Granting Request for an Extension, 8/13/2026), with Liberty separately filing a Motion for Expedited Treatment the same day as the second extension order (8/13/2026) -- i.e., movement, but the case remains open/pending with no tariff terms yet approved. This is the most recent PSC filing activity of the four MO instruments (as late as 8/13/2026, within days of the collection window) and should be watched on the next maintenance pass. MO GATE 2026-08-20: CONSTRUCTED TABLE QUOTE FIXED. The stored quote interleaved the EFIS filings table's data-label HTML ATTRIBUTE values ("Item No.", "Date Filed", "Filed on Behalf of") between the table's cell values. Those labels are CSS generated content (site.min.css: table.tableCollapse td::before{content:attr(data-label)}), rendered only at narrow viewports; they appear nowhere in the served bytes, so the quote could not reproduce on any raw fetch. Every FACT the row asserted re-confirmed against this gate's own curl fetch; quote re-cut from the page's own contiguous text (the hidden sortText span supplies the ISO datetime that precedes each printed date). - Utility Tariffs for Large Load Customers | Missouri Public Service Commission government two-reviewer
“Submit Comment in Liberty Case ET-2026-0184”
main body text, links section
https://psc.mo.gov/General/Utility_Tariffs_for_Large_Load_Customers
Link text and href (https://efis.psc.mo.gov/PublicComment/EmailForm) confirm docket number ET-2026-0184 for the pending Liberty Utilities large-load case; page also states "Liberty Utilities' large load tariff case is currently in progress." - Utility Tariffs for Large Load Customers in Missouri government two-reviewer
“Two of Missouri’s three regulated electric utility companies, Ameren Missouri and Evergy, have approved large-load tariffs. Liberty Utilities’ large load tariff case is currently in progress. ... Submit Comment in Liberty Case ET-2026-0184”
para. 1; footer links
https://psc.mo.gov/General/Utility_Tariffs_for_Large_Load_Customers
Official PSC overview page; also the source for the generic 12-year term/5-year ramp/80% minimum demand/2-year collateral/24-month exit-notice provisions description and the direct links to the Ameren tariff (efis.psc.mo.gov/Document/Display/859644) and Evergy tariff PDF. - Customer Wins in Liberty Electric Rate Case advocacy two-reviewer
“In February 2025, Liberty Electric Utility (also known as Empire District Electric Company), asked for a $152 million electric rate case (29.64%). Liberty already had the highest electric rates in Missouri... on January 14, 2026, the PSC approved a conditional rate increase of $97 million, phased in over a 3-year period... For more information, see Case No. ER-2024-0261”
paras. 1, 5, 9
https://moconsumers.org/utilities/customer-wins-in-liberty-electric-rate-case/
This is Liberty's general base-rate case (ER-2024-0261), not the separate large-load/data-center tariff case (ET-2026-0184); included for context per task 3/5 since it is the only public Liberty proceeding with a substantive outcome as of collection date. Author: Sandra Padgett, Consumers Council of Missouri.