AEP Ohio Distribution Rate Case, New Minimum Monthly Customer Charge for Data Centers (PUCO Case No. 25-392-EL-AIR)
single-reviewer order approved oh-puco-25392-el-air-aep-ratecase-dc-charge
Record created 2026-08-20, last updated 2026-08-26. Snapshot built September 14, 2026. JSON
Fields, as recorded
- State
- OH
- Kind
- order
- Status
- approved
- Agency
- Public Utilities Commission of Ohio (PUCO)
- Utility
- AEP Ohio (Ohio Power Company)
- Citation
- Pub. Util. Comm. Ohio Case No. 25-392-EL-AIR (AEP Ohio distribution rate case); companion Case No. 25-971-EL-UNC (bill format), Opinion and Order (April 1, 2026)
- Docket
- 25-392-EL-AIR
- Effective
- 2026-04-01
- Mandatory
- $99 Ohio pass
- Summary
- $99 Ohio pass
- Cost allocation
- $99 Ohio pass
- Locked fields
- $99 Ohio pass 3 recorded fields on this record are in the state and all-states passes.
Sources
3 rows, every one with a quote and a pinpoint. 3 quotes open here- PUCO issues order on AEP Ohio's distribution rate case, updates bill format (press release) government two-reviewer
“COLUMBUS, OH (April 1, 2026) – Today the Public Utilities Commission of Ohio (PUCO) ordered AEP Ohio to implement new distribution rates that will reduce its annual revenues by approximately $58.7 million.”
Body, opening sentence
https://puco.ohio.gov/news/aep-rate-case-2026
Fetched directly via curl. Same press release also states the settlement increases base distribution revenues by $11 million versus a $97 million utility request, sets a 9.84% authorized ROE, and returns ~$105 million to customers over 18 months under the Tax Cuts and Jobs Act. - PUCO issues order on AEP Ohio's distribution rate case, updates bill format (press release) government two-reviewer
“AEP Ohio will institute a minimum monthly customer charge for new data center customers. In its order, the Commission highlighted this provision builds upon the PUCO’s previous order to create a specific data center tariff, to ensure data center customers pay for the costs they impose on the grid.”
Body, fourth paragraph
https://puco.ohio.gov/news/aep-rate-case-2026 - PUCO issues order on AEP Ohio's distribution rate case, updates bill format (press release) government two-reviewer
“A copy of today’s opinion and orders is available online at PUCO.ohio.gov by clicking on the link to “Docketing Information System” and searching cases 25-392-EL-AIR (rate case) and 25-971-EL-UNC (bill format)”
Body, closing sentence
https://puco.ohio.gov/news/aep-rate-case-2026
Source of both docket numbers recorded on this instrument.