Batch Zero Process for Large Load Interconnections (ERCOT NPRR1325 / PGRR145)

two-reviewer regulation approved tx-ercot-nprr1325-pgrr145-batchzero-large-load

This record is listed in full and read in part. Its identity, citation, docket, status and review state are open, and so are all 6 of its source documents with their pinpoints, so you can go read the primary text yourself. The first 3 extracted quotes are open too. The recorded term fields, and the remaining quotes, are in the $99 Texas pass and the $199 all-states pass. Pricing.

Record created 2026-08-20, last updated 2026-08-20. Snapshot built September 14, 2026. JSON

Fields, as recorded

State
TX
Kind
regulation
Status
approved
Agency
ERCOT (Electric Reliability Council of Texas); Public Utility Commission of Texas (approval authority)
Citation
ERCOT Nodal Protocol Revision Request NPRR1325, 'Related to PGRR145, Batch Zero Process for Large Load Interconnections,' approved by the Public Utility Commission of Texas in Project No. 54445, Review of Protocols Adopted by the Independent Organization
Docket
Project No. 54445 (PUCT protocol-review project under which NPRR1325 was approved; NPRR1325/PGRR145 are ERCOT's own revision-request identifiers, not PUCT docket numbers)
Effective
2026-07-11
Mandatory
$99 Texas pass
Summary
$99 Texas pass
Locked fields
$99 Texas pass 2 recorded fields on this record are in the state and all-states passes.

Sources

6 rows, every one with a quote and a pinpoint. 3 quotes open here